Clarity

 View Only

 Project WBS/Schedule Migration capabilities from other platform/tool to Clarity SaaS

Dimitris Tranoudis's profile image
Dimitris Tranoudis posted May 23, 2025 05:00 AM

A prospect customer is asking on the available approach to migrate with confidence 40 complex WF projects from their current platform

to Clarity SaaS.  What options can we review with them?

Currently, there is no CSV import in the Tasks Object in the Modern Experience or in the Classic Experience.

Can MS Project or Open WorkBench project schedulers be used as a bridge between the two systems via syncing?

https://techdocs.broadcom.com/us/en/ca-enterprise-software/business-management/clarity-project-and-portfolio-management-ppm-on-demand/15-6/using/getting-started-with-classic-ppm/project-management/msp-manage-projects-with-microsoft-project/msp-synchronize-microsoft-project-with-ca-clarity-ppm.html

Has the proposed process been tested? Any Issues?

Alternatively, is there an approved add-on to import project tasks?

Any advice / hint will be much appreciated.

Herve ONNO's profile image
Herve ONNO

Hello,

you can used the  XOG option to import information; for the task you can use the prj_projects_wbs_dep_write.xml.

Regards