Hello,
I'm working with Clarity PPM version/build 16.1.0.959.01.39 (Preprod Environement).
Doing tests in Clarity, after creating a project with basic information (mandatory), added a team member and creating a task, when entering Timesheets (new interface) to register time, in some cases, the application registers the time added but also adds values on the ETC column.
Example - after adding 2 days, the application adds 0.5 days in ETC column (with no ETC entered previously).
Can you help me understand why the application has this behavier.
Thank you