Hi, dear colleagues!
Here is the interesting question. From time to time we are making transfers of our protected VMs from proteced site to reserve one for some tests. These tests usually require much time (week or more). We do it via "Test recovery plan" option, but here is a problem: in this case replications do not stop and increasing delta files eat space on protected site datastores up to 2x size from initial.
To stop this from happening i would like to use not "Test recovery" option, but to make a normal "Run recovery plan". But in this case there is a step to "Power off VMs on protected site". And i have found no ways to disable it, because we need these VMs up and running.
Can anybody advice any solution?
PS: Pausing replications do not help, delta still continues to increase.