Ok so the deployment seems ok as the import process should also convert any v6 uprocs into v7 uprocs. Is this windows or another OS?
Few things to check
- Can any uprocs at all be run on the v7 node, even if it is is just a basic uproc that just completes with a fail or a success. Trying to prove normal node operation
- Are all the environmental elements for the new BV uprocs present on the new node such as application, domain?
- If uprocs can run ok on the v7 node then can any of the uprocs on the new BV be run individually?
If still no joy then change the logging on the node settings to 0,TRACE,SECURITY, then save node settings and try running the new uprocs again and then check the node log for any obvious messages.
Switch the logging back to previous after testing as TRACE will put a lot of entries into the universe log.