Some things to check:
Resource OBS vs Staff OBS. Are there resources/roles that may have a different staff OBS than resource OBS?
Are all active?
Is this a different environment showing 4 than production?
------------------------------
Liz Williamson
Sr. Support Engineer - Clarity
Broadcom
------------------------------
Original Message:
Sent: 06-23-2021 10:31 AM
From: Jaya Santosh Kumar Patchipulusu
Subject: Please share me Capacity Planning overview portlet guide
I have run the Capacity overview, but the data on the OBS level doesn't seem clear
What does the 4.00 for june 2021 represent? Is it 4 hours? Production was showing 17.00
Original Message:
Sent: 05-15-2021 11:21 AM
From: Martti Kinnunen
Subject: Please share me Capacity Planning overview portlet guide
Not exactly a guide, but there is description in the portlet refernce in the documentantion. See
https://techdocs.broadcom.com/us/en/ca-enterprise-software/business-management/clarity-project-and-portfolio-management-ppm-on-premise/15-9-2/reference/clarity-ppm-portlets-reference.html#concept.dita_39c808bf98eb0866ddad9af85a9a885c35541654_CapacityOverviewPortlet
Original Message:
Sent: 05-15-2021 07:22 AM
From: Jaya Santosh Kumar Patchipulusu
Subject: Please share me Capacity Planning overview portlet guide
Hi All - I tried searching for Capacity planning overview portlet, but couldn't find related Docs. ( Home --> resource management --> Capacity Planning Overview ).