Task constraint defaulting to 'finish no earlier than'

Jump to Best Answer
  • 1.  Task constraint defaulting to 'finish no earlier than'

    Posted 26 days ago
    Hi there,
    When I create a new task in the 'gantt' chart in Clarity I do not select any constraint at all. But when I go into msproject and look at the constraint types for the tasks I have just created in Clarity it seems like they are defaulting to 'finish no earlier than'. Is there any way I can change the default 'constraint' to 'must start on' without having to set a date for the 'must start on' for every new task I create?

    Thanks, Tim


    ------------------------------
    Tim Munns
    ------------------------------


  • 2.  RE: Task constraint defaulting to 'finish no earlier than'
    Best Answer

    Posted 24 days ago
    Hi Tim,
    Please check the following thread:
    Clarity PPM
    Broadcom remove preview
    Clarity PPM
    Hidden page that shows all messages in a thread
    View this on Broadcom >
    Regards
    Joxi