Clarity

 View Only
Expand all | Collapse all

Task constraint defaulting to 'finish no earlier than'

  • 1.  Task constraint defaulting to 'finish no earlier than'

    Posted Jun 24, 2019 11:46 PM
    Hi there,
    When I create a new task in the 'gantt' chart in Clarity I do not select any constraint at all. But when I go into msproject and look at the constraint types for the tasks I have just created in Clarity it seems like they are defaulting to 'finish no earlier than'. Is there any way I can change the default 'constraint' to 'must start on' without having to set a date for the 'must start on' for every new task I create?

    Thanks, Tim


    ------------------------------
    Tim Munns
    ------------------------------


  • 2.  RE: Task constraint defaulting to 'finish no earlier than'
    Best Answer

    Broadcom Employee
    Posted Jun 26, 2019 09:23 AM
    Hi Tim,
    Please check the following thread:
    Clarity PPM
    Broadcom remove preview
    Clarity PPM
    Hidden page that shows all messages in a thread
    View this on Broadcom >
    Regards
    Joxi