  • 1.  Hours in UI do not match hours in Classic Clarity

    Posted Oct 06, 2020 05:16 PM
    The following are the hours in Workbench, which are the same in Clarity
    Task  % complete  Resource ETC Actuals
    Sprint15 30% R1 20 20
        R2 40  
        R3 40 40
        R4 20  
        R5 70 10
        R6 50 30
        R7 4 0
        R8 2 6
    Total 246 106

    This is what shows up in the new UI


  • 2.  RE: Hours in UI do not match hours in Classic Clarity

    Posted Oct 07, 2020 02:15 AM
    Which figures are displayed, when you switch to "hours" and "days" via the user's settings on the top right -> "General" -> Unit of Measure? I would assume, that it is currently set to FTE, but still the figures dont seem to add up...

    ------------------------------
    IT Service Manager
    SCHOTT AG
    ------------------------------



  • 3.  RE: Hours in UI do not match hours in Classic Clarity

    Posted Oct 07, 2020 11:57 AM
    In the Admin Classic>Project Management>Settings>General.... "Default display for work effort" it is set to hours.
    Is there somewhere else we can change this setting?
    I didn't find anything in the Task Grid itself only Decimal places.


  • 4.  RE: Hours in UI do not match hours in Classic Clarity

    Broadcom Employee
    Posted Oct 07, 2020 12:17 PM
    HI Konda

    Please check out KB https://knowledge.broadcom.com/external/article?articleId=200076 

    Hope this helps!

    ------------------------------
    Nika Hadzhikidi
    Sr Principal Support Engineer
    Broadcom
    ------------------------------



  • 5.  RE: Hours in UI do not match hours in Classic Clarity

    Posted Oct 07, 2020 04:32 PM
    Thanks so much! I changed it and the hours look good. The FTE however did not equal hours.
    in the example above Actuals total hours were 246
    The task total hours was 1.33


  • 6.  RE: Hours in UI do not match hours in Classic Clarity

    Posted Oct 08, 2020 04:16 AM
    Just wondering again...
    How does that work?
    If you have 
    106 hours and 8 hour day you get 13.25 not 1.3
    246 hours you get 30.75 not 3.08

    What am I missing?


  • 7.  RE: Hours in UI do not match hours in Classic Clarity

    Posted Oct 09, 2020 02:29 AM
    Without knowing the exact figures per period incl. the assignment/allocation timeframe, a calculation might not lead to the correct result.
    If the ETC for one month = 20 Days you would expect 1 ETC in FTE, if the assignment falls exactly into one month.
    If the Assignment exceeds this one month, the FTE figure will decrease. For example: 20Days ETC for an assignment of 2 months are still 20 Days, but only 0,5 ETC as FTE.
    It's just a best guess, without the exact figures.

    ------------------------------