Hi Andre,
this issue has been fixed with 21.0.12
https://downloads.automic.com/tools/release_notes?lifecycle_entity_id=1409143059253&component_id=1409731986667&version_id=1698143192680&upgrade_version_id=1712578700440&search=inactive
Regards, Markus
Original Message:
Sent: Oct 07, 2024 09:17 AM
From: Andre Buettemeyer
Subject: Problem with task deactivation after Update to 21.0.10
After updating from version 21.0.8 to 21.0.10 we observe the following behavior.
A workflow, for example JOBP2, is integrated into another workflow, for example JOBP1.
JOBP2 is deactivated by removing the "Active" option in the General-Tab.
If JOBP1 is now started, JOBP2 remains under Process Monitoring with the status "ENDED_INACTIVE_OBJECT - Object is inactive due to definition".
We managed to deactivate the JOBP2 by setting the same status with "Modify Status Manually".
We informed our support.