AutoSys Workload Automation

  • 1.  Extended calendar for Holidays plus one

    Posted Sep 11, 2015 12:45 PM

    I have a standard Autosys calendar describing my company holidays.  I would like to make an extended calendar describing "holidays+1", that is, one day past each holiday, regardless of the kind of day it is.  For example, January 1st is a holiday so January 2nd would be in the calendar, November 26 and 27 are holidays so November 27 and 28 would be in the calendar.

     

    It seems like I should be able to do that with extended calendars but I don't know how.



  • 2.  Re: Extended calendar for Holidays plus one

    Broadcom Employee
    Posted Sep 11, 2015 01:36 PM

    Thanks for your post. I have moved this discussion to the "CA Workload Automation" community since you have described your question as being related to Autosys.



  • 3.  Re: Extended calendar for Holidays plus one

    Posted Sep 11, 2015 01:41 PM

    create an extended calendar using the days in the exclude calendar and say move forward a day if your date falls on the one in the calendar.



  • 4.  Re: Extended calendar for Holidays plus one

    Posted Sep 14, 2015 05:23 AM

    I would do the same, but wonder if all holidays definition fit into 255 characters.

     

    Or would define extended calendar using holiday dates and set adjustment to +1 day