Enhancement Request: Task actual finish date that is different than the date the last hour is posted on assignments

  • 1.  Enhancement Request: Task actual finish date that is different than the date the last hour is posted on assignments

    Posted Oct 29, 2015 05:41 PM

    Project Managers have requested that they have the ability to set the actual finish date on a task (in Clarity and MS Project) that is later than the date the last hour is posted on assignments. The Project Manager should be the one to determine when a task is completed, and just because the last hour is posted on an assignment does not mean that work was completed satisfactorily. The current work around is to use a milestone to mark the actual finish date, but you lose the duration variance of the task.



  • 2.  Re: Enhancement Request: Task actual finish date that is different than the date the last hour is posted on assignments

    Posted Oct 29, 2015 06:15 PM

    Did you post this in ideation? where the ERQ shuold go.

    Another work around should be to leave a little ETC on the assignments.



  • 3.  Re: Enhancement Request: Task actual finish date that is different than the date the last hour is posted on assignments

    Posted Oct 29, 2015 06:39 PM

    Reposted in Ideas. Thanks.



  • 4.  Re: Enhancement Request: Task actual finish date that is different than the date the last hour is posted on assignments

    Posted Oct 30, 2015 04:49 PM