  • 1.  Microsoft Project 2010 - MSP 2010

    Posted Dec 29, 2010 02:18 PM
    I have read threads here that indicate the interface between MSP 2010 and Clarity is available in Q1 2011. Once the interface for 2010 is available, will we need to upgrade to a new release of Clarity? Or is it possible to get just the MSP 2010 update?

    Also - Does anyone know if CA is still on target for the release? I'm working through our sales rep on this as well, but looking for any more immediate answers that may be available. Thanks!


  • 2.  RE: Microsoft Project 2010 - MSP 2010

     
    Posted Dec 29, 2010 02:32 PM
    Hi,

    I checked with Support on this and below is the response. Hope this helps.

    "MSP 2010 will be compatible with 12.1.1
    it will not be backward compatible with earlier versions of Clarity"

    As for release date they don't have an exact date but understand it to be Q1.

    Regards,
    Chris


  • 3.  RE: Microsoft Project 2010 - MSP 2010

    Posted Sep 24, 2011 01:07 PM
    Can we get an update on this. What does it mean that it won't be backward compatible? Does that mean if we move to MSP 2010 that we won't be allowed to use any of the previous versions of MSP with Clarity?


  • 4.  RE: Microsoft Project 2010 - MSP 2010

    Posted Sep 25, 2011 04:52 AM
    My understanding of
    "MSP 2010 will be compatible with 12.1.1 it will not be backward compatible with earlier versions of Clarity"
    is that MSP 2010 will not be backward compatible whit earlier versions of Clarity

    There release notes for v12.1SP 1 say under

    Clients
    The following table shows supported software for client machines accessing CA Clarity  PPM. 

    ■ Microsoft Project 2007 ‐ 2010, all editions 
     

    while
    Using CA Clarity PPM with Open Workbench
    and Microsoft Project
    v12.1.0 Service Pack 1

    says

    Before you Install CA Clarity PPM Microsoft Project Interface
    Before you install CA Clarity PPM Microsoft Project Interface, ensure that you meet the
    following criteria:
    ■ Microsoft Project Professional 2010 is installed with the
    office-kb2075992-fullfile-x86-glb.exe patch applied:
    ■ Microsoft .NET Framework 4 (dotNetFx40_Full_x86_x64.exe) is installed.
    ■ Microsoft Visual Studio 2010 Tools for Office Runtime (vstor40_x86.exe) is installed

    Though that is not quite accurate according to
    Clarity 12.1 SP1 & MSP 2010 Weird Behaviors
    49768546


    but I would not expect any of those three installs to prevent using earlier versions of MS Project on the same workstations if you uninstalled 2010 first.

    I don't think the above says anything about using different versions of MS Project on different workstations to access the one and same Clarity.

    Martti K.


  • 5.  RE: Microsoft Project 2010 - MSP 2010

    Posted Sep 26, 2011 02:30 PM
    ... in the mean time elsewhere in the web

    Readme for 12.1.1.1 003

    CLRT-63051: MSP: Fix for CLRT-59078/59079 prevents all MSP users from being able to upgrade their MSP versions once they upgrade Clarity to 12.1.1 and higher or 13 and higher (TEC550798)

    Martti K.