Hi everyone,
This is my first thread here so I sorry in advance if this broke any rule or anything.
I am hoping the community can advise on a critical issue we have faced for 6 months with a customer's 3-node VxRail cluster.
We are stuck in a loop between Broadcom, Dell, and our distributor, leaving the customer without support.
Here is the situation in simple terms:
-
The Setup
-
3-node VxRail cluster currently located at a customer data center site.
-
Currently as per now it is out of support (no hardware support, no VMware subscription, no latest VMware patches).
-
Customer only needs 1 year of renewal (until Dec 2025).
-
What We Tried
-
Step 1: Contacted our MSP for VMware Cloud Foundation (VCF) subscription renewal (post-Broadcom takeover). MSP agree to provide VCF subscription.
-
Step 2: Approached distributor for VxRail hardware support renewal.
→ Distributor said: "Dell would not allow MSP software approach to be tie with hardware support renewal" reason being "Broadcom does not allow it due to account number of VCF license is under MSP"
-
Step 3: Went directly to Broadcom for VCF license.
→ Broadcom provided a quote + account number. License purchase process started
-
Step 4: Shared Broadcom account detail with distributor. Distributor forward to Dell for BYOL ("Bring Your Own License") which we use before for VxRail hardware support renewal.
→ Dell said: "BYOL no longer valid." due to Broadcom say so.
-
Step 5: Approach back to Broadcom. They confirmed their license was fine but advised on canceling the purchase. Proceed to cancel.
-
Step 6: Approach back to Distributor for purchasing software + hardware support (VCF with account number under customer name + VxRail support renewal). Dell then said: "VMware purchases on hold". No timeframe given on how long this hold will be
-
Current Crisis
We've been pushed between local DELL, Broadcom and Distributor teams for 6+ months with zero resolution.
Question to the Community:
-
Has anyone faced similar hurdles renewing VxRail hardware support + VMware licensing post-Broadcom transition?
-
Any workarounds to break this deadlock?
-
Who at Broadcom/Dell can escalate this?
Footnote:
- The customer is exposed and frustrated.
- The customer patient already in razor thin status as 6 months have pass without any clear resolution.
- We cannot approach or swap to other MSP or distributor as Broadcom only pointed 1 MSP and 1 distributor for the whole country (which is the one we approach by the way).
Any advice on how to solve this would be great.