you may have to use opt cards with the content Lvl=6 Phase 1 or Phase 2
compiles will have new warning messages, take note of those messages
What worked in Cobol4 may not work in cobol 6
------------------------------
Derez Lusk
------------------------------
Original Message:
Sent: 06-04-2020 08:54 AM
From: Piyush Bhardwaj
Subject: Cobol 6.2 Upgrade
Hi,
My shop is planning to upgrade Cobol from 4.2 to 6.2.What could be the best approach considering we have 4 Endevor Instances.Using BSTXCOPY for PDS conversions of COBOL Load libs. Any suggestions will be appreciated......