  • 1.  Daily plan in CA-7

    Posted Jul 06, 2018 04:25 AM

    Hello everyone,

     

    I have always worked with schedulers other than CA-7, but soon I will start doing it with CA-7.

     

    In the installation that CA-7 uses, they tell me that it does not have an expansion of the daily plan, as it is done with other schedulers. Is this generic for all installations with CA-7?

     

    thanks and best regards,

    Davagar



  • 2.  Re: Daily plan in CA-7

    Broadcom Employee
    Posted Jul 06, 2018 08:32 AM

    Hi David,

     

    I am unclear as to what you mean by "expansion of the daily plan".  Can you please explain.

     

    Thanks, Roderick (CA Support)

     



  • 3.  Re: Daily plan in CA-7

    Posted Jul 06, 2018 12:38 PM

    In some schedulers, a job is responsible for scheduling in the queue the jobs that must be executed that day. And so every day. Otherwise, nothing would be executed.

     

    In the new client that I'm going to work, they tell me that CA-7 does not work that way.

     

    Thanks RODERICK



  • 4.  Re: Daily plan in CA-7

    Broadcom Employee
    Posted Jul 06, 2018 03:09 PM

    Ok, I see what you saying. CA 7 schedule scan (SSCAN) mechanism brings jobs in incrementally throughout the day based on scheduling criteria. It is not a once a day run that dumps all the days workload into the queue.  



  • 5.  Re: Daily plan in CA-7

    Posted Jul 09, 2018 02:25 AM

    Thank you very much for your answer!, Roderick