Hi Lowell,
Instead of the ACWP, would you be interested in getting the 'Actual Costs' at the assignment level?
Assignment Actual Costs is available from the 'Assignments' Module
You can add the column to the grid by periods and you can export it to CSV format.
Original Message:
Sent: Nov 17, 2022 10:16 PM
From: Lowell Wetzel
Subject: Query to pull ACWP
I am looking to pull the ACWP value.
I see there are calculations for Project, but I do not see an example query to pull this value. Does anyone have a query that can pull the ACWP?
Project
ACWP = Sum of ACWP for all summary tasks in project