Hi
We've got a number of Projects where the finish date of a task has been pushed out to the end of 2017 (29/12/17). The resource allocated to the task are allocated to the end of 2017 and have ETC.
When the resource books time in Nov 16 to the task and we run the Post Timesheet job the finish date of the task is being changed to the latest date of the booked time e.g. 11/11/16. This is happening on a number of Projects but not on most of them.
Does anyone have any idea why this is happening? I'd expect it to move the finish date out if the time booked was later than the finish date on the task but not the other way round.
Thanks
Richard