Hey Markus
I did enter an api but given the attribute is against the cost object and not the project object it's not coming through the new UX. If l'm wrong can someone please advise me if there is a work around pleasseeeeee lol.
Cheers,
Tony
Original Message:
Sent: 08-23-2019 02:56 AM
From: Markus Franke
Subject: Budget Type field in new ux
Hi Tony,
you have to provide an "API-Attribut-ID" for the attribute. Then you can use your custom attribut in New UX.
Regards
Markus
Original Message:
Sent: 08-22-2019 01:32 AM
From: Antonio Montano
Subject: Budget Type field in new ux
I just noticed that its a custom attribute (Budget Type) under the cost plan object so can I assume custom attributes under this object are not available in the new UX yet?
Cheers,
Tony
Original Message:
Sent: 08-22-2019 01:26 AM
From: Antonio Montano
Subject: Budget Type field in new ux
Hi guys
I'm just wondering if anyone has come across when approving a cost plan to a budget plan in the UX there is no "Budget Type" field. We use this attribute to differentiate between 'Adopted Budget' and "Revised Budget'. The revised budget being used to push through change requests.
If someone can enlighten me that would be great
Cheers,
Tony