Hello,
if you add resource to the task for example from gantt to the task his ETC is autopopulated based on his % of allocation for time period of task.
Is there any possibility to disable this auto fill ETC functionality?
Vit
Hi Vit,
If the resource has a planned allocation, ETC value will be given for that resource. If you remove the planned allocation then the ETC will become '0' when assigning that resource to a project. Currently this is by design and unfortunately there is no way to disable this feature. Please let us know if this has answered your question. Thank you!
Kind regards,
Tabish Siddiqui
Thank you Tabish,
I asked just for confirmation if I didn´t miss something.