Hi Martink,
Iam using clarity v13.1 and OWB 2.0.
I can able to change the Task Finish date in OWB it is changing in OWB.But when i save back this project to clarity. The chages are not there.
The dates are reversed to the early dates.(The task is a fixed duration task and loading pattern is "counter" and there are actuals posted in this task).
Why the task Finsh date which was changed in OWB is not changing when save this project back to clarity.
I am doing this with my admin login .I don't think this was due to some access related issues.
can you please tell what could be the possible sollution for this
Thanks
Rajesh