Just to add on to what David said... The Parent stories
Schedule State is a reflection of the
Schedule State of values of its children. You can't manually set the parent's
Schedule State. it automatically gets set based on the values of its children. So if one child is not
Accepted, the parent will not show as
Accepted. Think of the parent story as just a
container for the children. There are a few fields like this when you have a parent story:
Release, Iteration, Planned Estimate; all based on the value of its children.
What's the reason you want to show the parent as
Accepted , when the child stories are not all
Accepted ?
Original Message:
Sent: 03-25-2020 09:42 PM
From: Heather Todd
Subject: Parent story won't move to Accepted column
Hi
We are having an issue on the Team Board where we've completed and accepted all the child stories and they have moved from the Completed column to the Accepted column. But the Parent story will not move to the Accepted column, we drag it across and it just reverts back to the Completed column. If we remove all child stories it will move across, but that is really not a good option for us.
Does anyone have any suggestions?
Thanks