New User Experience Roadmap - Synching

  • 1.  New User Experience Roadmap - Synching

    Posted 6 days ago
    Hi Everyone, 

    When I go to Roadmap and sync the start date and finish date for all the projects that I included in the roadmap, I am getting this below error message. Any Idea ?

    API-1006 : The value 'start_date,finish_date' for Attribute '{1}' is not in expected format or is invalid



  • 2.  RE: New User Experience Roadmap - Synching

    Posted 5 days ago
    can you check the attribute start and finish date API in project as per the error.

    ------------------------------
    Thanks & Regards
    Suman Pramanik
    Principal Support Engineer | Customer Success & Support, Enterprise Software Division
    Broadcom
    ------------------------------



  • 3.  RE: New User Experience Roadmap - Synching

    Posted 5 days ago
    Hi Suman, 

    It is happening only for Start Date. I checked the API setup and it looks good. I tried synching only Finish Date, it is synching well alone with the finish date.