  • 1.  Portfolio Items % Complete (story count and plan estimate) not updating

    Posted Jun 04, 2020 02:39 PM
    Edited by Henry Reimert Jun 04, 2020 03:20 PM
    Has any seen where the percent complete fields on Portfolio Items is not updating when child items (User Stories) are moved to Accepted? I have several examples where it is saying "Last Rollup Date 2020-05-04" when there were changes to the stories 2020-06-03 and 2020-06-04. In the same Workspace and different Workspaces, it is working fine.

    I see a similar question asked here - https://community.broadcom.com/enterprisesoftware/communities/community-home/digestviewer/viewthread?GroupId=2437&MessageKey=873d90f6-07b5-47ab-bdf1-2ff62fbee158&CommunityKey=f303f769-8d4c-44d9-924c-3845bba6444e&tab=digestviewer&ReturnUrl=%2fenterprisesoftware%2fcommunities%2fcommunity-home%2fdigestviewer%3fcommunitykey%3df303f769-8d4c-44d9-924c-3845bba6444e%26tab%3ddigestviewer, but I don't think there was a definitive answer.


  • 2.  RE: Portfolio Items % Complete (story count and plan estimate) not updating
    Best Answer

    Broadcom Employee
    Posted Jun 04, 2020 05:31 PM
    Hi Henry,

    THere has been an ongoing issue with this recently, but we think we have a solution. If it is still happening for you, please could you raise a support ticket on our website and the folks will look into it?

    Thanks,

    ------------------------------
    Nik
    Ask me a question, I'm All Ears!
    Rally Sales Engineer
    Rally Software
    ------------------------------



  • 3.  RE: Portfolio Items % Complete (story count and plan estimate) not updating

    Posted Jun 05, 2020 07:32 AM
    I checked all of the items this morning and they have all updated. I will raise a ticket if we see it again. Thank you!