  • 1.  Capacity Planning- Rally

    Posted Dec 23, 2021 07:54 PM
    Is it possible to load resources , update availability to plan for velocity/capacity for each iteration. Typically this is done outside the ALM tool using spreadsheet. but does rally have build in capability for capacity planning


  • 2.  RE: Capacity Planning- Rally

    Broadcom Employee
    Posted Jan 04, 2022 10:35 AM

    Track > Team Status allows users to define their Project-level Capacity by Iteration.

    Plan > Team Planning  and Plan > Timeboxes > Iterations both allow for the definition of (Planned) Velocity for each Iteration.

    The two values (Capacity & Velocity) do not interact.



    ------------------------------
    [Rally Software]
    ------------------------------