Hi Denis,
It is not clear whether you have created your own timesheet app or whether you are using the inbuilt one. I assume because you are talking of a new field called Balance Hours that you have created something yourself.
What sort of field did you make "Balance Hours"? There are two types of field you can use Integer or Decimal. The integer is positive numbers only - Decimal will deal with negative numbers.
Revised answer! Oh I get it! You are adding extra stories and extra tasks to handle the balance and then tryinfg to add negative numbers into the inbuilt TimeSheet.
That won't work unfortunately. The field is an Integer.
------------------------------
Nik
Rally Sales Engineer
Rally Software
------------------------------
Original Message:
Sent: 01-08-2020 11:56 AM
From: Denis Pertsev
Subject: how to handle flex or balance hours with Rally Dev
Hello community,
I been trying to implement balance hours for our company and for this I did User Story for one year with name "Balance Hours"
where each employee will have own balance hours, and report it accordingly in TimeSeet
The rule was:
1) if you did extra you add hours to your balance task how many extra hours you did in this day.
2) if you use balance hours you add balance hours with minus.
Timesheet example
User Story Task 7th Jan 8Jan 9Jan
Customer US TaskX 12 8 4
Balance hours Balance +4 0 -4
But, ...... Unfortunately ... Rally did not support Negative Values in Timesheet.
Could anyone provide good suggestion to me how is it possible to handle balance with Rally?
Br, Denis