How can I prevent a User Story from automatically moving to complete if all its tasks are completed?

Jump to Best Answer
  • 1.  How can I prevent a User Story from automatically moving to complete if all its tasks are completed?

    Posted 01-05-2018 07:53 AM

    I have a custom kanban board with several columns specific to our dev flow. I noticed that when tasks of a User Story are all completed, the card automatically moves tot he first column of status Complete (in our case it is Biz Review, skipping Dev Review and QA Review)

     

    Is there a way to stop this default behavior of Rally?



  • 2.  Re: How can I prevent a User Story from automatically moving to complete if all its tasks are completed?
    Best Answer

     
    Posted 01-05-2018 04:42 PM

    Hi! Check out Task State Updates Parent Schedule State | CA Agile Central Help  for how to turn this logic off. If you have any questions, just let me know and I'm happy to help.

      -William



  • 3.  Re: How can I prevent a User Story from automatically moving to complete if all its tasks are completed?

    Posted 01-08-2018 05:01 AM

    Many thanks William. This is really helpful