    DE37518 - Invalid % Done on Portfolio Items Restored from the Recycle Bin
    DE38462 - The Plan Progression page will not load data on certain plans
    DE38613 - Can not edit Scheduled States.
    DE38585 - Workspace admin cannot create new user in Agile Central - all buttons are missing
    DE38616 - Release & Iteration Burndown Chart Doesn't Load
    DE34052 - Filter by Release or Iteration value clears when changing Project
    DE34302 - Add/Remove Projects on Milestone (new feature) displays project selection as "All Projects in WS" instead of selected project(s) on grids
    DE37282 - Team Board doesn't display stories in the last column depending on how the last column was added
    DE38266 - Iteration SummaryApp shows 0 days remaining for a future iteration
    DE38188 - Planner check box shows up even if the Subscription is not Unlimited

     