General use case: The project is set on hold for 2 months and should be rescheduled based on this. In other words, we have to reschedule the project with today + 2 months and keep all dependencies.
1. Resources have hard allocation based on the project plan
2. The project manager has SoftAllocation right only
3. Mixed booking is not allowed
Usage of rescheduling function in the PPM Gantt chart is not the solution, because if resources don't have any allocation for the project in the future, tasks are rescheduled to time after project finish.
We found a way but its really complicated and need Resource Manager action and it's not accepted by Customer
Anybody with an idea?
Vit
------------------------------
Consultant
Catta Consulting
Czech Republic
------------------------------