I'm so very sorry for you, the bad news you can't do this if people are charging time to the tasks
The little bit better news. ..... you can copy paste task name, dates, predecessors and successors from Excel
I would highly recommend or insist that unless you know what you are doing I mean really really know what you are doing that you don't do it from MSP!
Why? Because if
1. there are actuals on the tasks the msp file saved offline may/will differ from the project in Clarity. Clarity will not let you put the project back into Clarity.
2. the really really terrible news.... if you have admin rights or resource create rights and you copy paste the file from the MSP offline snapshot and someone clicked even an "A" in the resource column.... MSP is notorious for creating rogue resources.... Since you have godly type rights Clarity assumes (haha) you know what you are doing and will create this new resource..... which will cause you all kinds of heart ache!
Hope this helps
------------------------------
Sys Admin
CPS Energy - Texas
------------------------------
Original Message:
Sent: 08-07-2019 06:13 AM
From: Vit Posel
Subject: Restore a project schedule including resource assignments from saved point
Did anybody solved a requirement - Restore a project schedule including resource assignments from ?
I know sophisticated but only one solution I see currently in saving as MSP snapshot offline and replace back if needed (not tested)
any other idea?
Vit
------------------------------
Consultant
Catta Consulting
Czech Republic
------------------------------