Products
Applications
Support
Company
How To Buy
Skip to main content (Press Enter).
Sign in
Skip auxiliary navigation (Press Enter).
Register
Skip main navigation (Press Enter).
Toggle navigation
Search Options
Home
Communities
All Communities
Enterprise Software
Mainframe Software
Symantec Enterprise
Blogs
All Blogs
Enterprise Software
Mainframe Software
Symantec Enterprise
Events
All Events
Enterprise Software
Mainframe Software
Symantec Enterprise
VMware
Water Cooler
Groups
Enterprise Software
Mainframe Software
Symantec Enterprise
Members
Clarity
Private Community
View Only
Community Home
Threads
Library
Events
Members
Back to discussions
Expand all
|
Collapse all
sort by most recent
sort by thread
Baseline work wrongly displayed
Jump to
Best Answer
Patrick SCHWARTZ
Mar 26, 2020 10:52 AM
Hi, We are using projects and subprojects and when displaying the Baseline Work in the Hierarchy / Effort ...
Liz Williamson
Mar 27, 2020 09:35 AM
Best Answer
Hello Patrick, I did look at this and it appears it may be a bug. If nobody else has an explanation ...
1.
Baseline work wrongly displayed
0
Recommend
Patrick SCHWARTZ
Posted Mar 26, 2020 10:52 AM
Reply
Reply Privately
Options Dropdown
Hi,
We are using projects and subprojects and when displaying the Baseline Work in the Hierarchy / Effort roll up menu entry for a project, we have a wrong display of it :
Project PRJ049197 being composed of the last 3 subprojects and itself, we were waiting a total of 314 md = 60 + 45 + 5 + 204 (which the baseline work for the project itself)
Could you help on how solving this issue ?
Regards
2.
RE: Baseline work wrongly displayed
Best Answer
0
Recommend
Broadcom Employee
Liz Williamson
Posted Mar 27, 2020 09:35 AM
Reply
Reply Privately
Options Dropdown
Hello Patrick,
I did look at this and it appears it may be a bug. If nobody else has an explanation would you please raise a case with Clarity support.
Thank you,
Liz Williamson
Original Message
Original Message:
Sent: 03-26-2020 09:06 AM
From: Patrick SCHWARTZ
Subject: Baseline work wrongly displayed
Hi,
We are using projects and subprojects and when displaying the Baseline Work in the Hierarchy / Effort roll up menu entry for a project, we have a wrong display of it :
Project PRJ049197 being composed of the last 3 subprojects and itself, we were waiting a total of 314 md = 60 + 45 + 5 + 204 (which the baseline work for the project itself)
Could you help on how solving this issue ?
Regards
×