  • 1.  Is_Late field is empty in Task Grid

    Posted Nov 20, 2019 12:45 AM
    Hi team,

    The is_late field in Task object is empty in Clarity New UI when configured in Task Grid.
    However, the same is displayed in Classic UI. Is that not Supported yet in NEW UI?

    We are in Clarity 15.6.1

    Regards,
    Divya


  • 2.  RE: Is_Late field is empty in Task Grid

    Broadcom Employee
    Posted Nov 20, 2019 04:16 AM

    Hi Divya, 

    The tasks that you are showing in the screenshot, are not having the value "Yes" to the field "Is Late", I believe. 

    Could you please check, if for a Task which has Is Late as Yes in Classic UI, is also showing the same way in New UX? 

    As per my knowledge, New UX does not show any value if the Is Late attribute is having "No" value for a task. 



    ------------------------------
    Abhisek Dhar
    Senior Engineer
    Clarity PPM Support
    ------------------------------



  • 3.  RE: Is_Late field is empty in Task Grid

    Posted Nov 21, 2019 12:01 AM
    Hi Abhishek,

    Yes if the task is Is_Late, then it ticked in New UI.
    Thank you.

    Regards,
    Divya


  • 4.  RE: Is_Late field is empty in Task Grid

    Broadcom Employee
    Posted Nov 21, 2019 03:38 AM
    Hi Divya, 

    Yes, that is what I was telling. It works fine in New UI, just the fact is, it does not show anything specific when a task is as per schedule and not late yet. :)

    ------------------------------
    Abhisek Dhar
    Senior Engineer
    Clarity PPM Support
    ------------------------------



  • 5.  RE: Is_Late field is empty in Task Grid
    Best Answer

    Broadcom Employee
    Posted Nov 20, 2019 12:41 PM
    The 'Is Late' is computed based on the following:
    You must have a Baseline Finish Date
    The computation looks at the Baseline Finish Date, the current Finish date on the task or milestone.

    If the current Task Date is later than the Task's Baseline Finish Date, this field is marked true.
    For example:
    Create a task with a Finish date set to Nov 13th.
    Create a Baseline
    'Is Late' field = FALSE
    Edit the task finish date to a later date such as Nov 15th.
    'Is Late' field = TRUE