  • 1.  New UX Team - posting Time

    Posted May 09, 2019 11:27 AM

    Hi every one,

     

    we are currently testing the new Team functionality. Is it possible that if a team is assigned to a project - that every one from the team should be able to post his time on this project without beeing assigned seperatly as named ressource?

     

    Chris_Hackett 

     

    Thanks for your help!



  • 2.  Re: New UX Team - posting Time
    Best Answer

    Posted May 09, 2019 12:43 PM

    The way I have seen it in the demos is that a team equals a named resource in the timesheets. So the time posted for a team goes to the team and not to the individual resources. At the same time a named resouce may post time for the same (project and task) and the actuals are kept separate.