I have a time-varying field with Date constraints. The field is configured in an object-based portlet. The time-varying field is editable within the constraints as expected for the most part.
When the start and finish dates are the same, I expect the field to be editable. But, it does not work that way. Am I missing something or is it the expected behaviour?
NOTE: The timestamp for Start Date is 8 AM and Finish Date is 5 PM