  • 1.  Cost Plan - Budget Plan Finish Date

    Posted May 09, 2018 04:55 AM

    Hi CA Community,

    Why do the Cost Plan created in the same day has Finish Period till May 2018, and once approved as Budget Plan it switches to March 2018?

    It is something that is amendable at any point?

    It changes the values as the date range differes between them.



  • 2.  Re: Cost Plan - Budget Plan Finish Date
    Best Answer

    Posted May 09, 2018 08:21 PM

    Yes, it is amendable. 

    Once you click on "Submit Plan of record for approval", you get a page as below:

    You can change the dates here and then submit for approval. 

     

    Hope this helps. 

     

    Thanks

    Shailey