  • 1.  Portlet to see baselined ETC vs timesheeted actuals on week detail

    Posted Sep 21, 2018 06:15 AM

    Hello on task assignment level is possible to see comparison of those two information but we are not able to have those in portlet overview for project.

     

    Any suggestion?

     

    Vit



  • 2.  Re: Portlet to see baselined ETC vs timesheeted actuals on week detail

    Posted Sep 21, 2018 09:30 AM

    See how close you can get with Weekly detail

    Baseline usage is the baselined usage. It does not care if it is ETC or Actuals

    You do not get timeentries in that, but you do get Actuals that is posted timeentries. If your time entry period is a week set the scale to weekly. If your tome period is something else your are out of luck.



  • 3.  Re: Portlet to see baselined ETC vs timesheeted actuals on week detail

    Posted Sep 24, 2018 04:03 AM

    Good Idea,

    thank You I will try to explain.



  • 4.  Re: Portlet to see baselined ETC vs timesheeted actuals on week detail

    Posted Sep 24, 2018 09:52 AM

    Sorry I forgot to write one more condition. Requirement is to see this on task detail not only on investment detail. Its requested the same way as its on assignment.

     

    Vit



  • 5.  Re: Portlet to see baselined ETC vs timesheeted actuals on week detail

    Posted Sep 24, 2018 11:42 AM

    You are out of luck. As far as I can see the Weekly detail data source does not include task name or ID.

    Then you have to resort to a query based portlet using timeslices.



  • 6.  Re: Portlet to see baselined ETC vs timesheeted actuals on week detail

    Posted Oct 03, 2018 06:51 AM

    Yep thats my idea too but I just asked if I didnt miss some OTB portlet with this functionality.

    Thank you urmas

     