  • 1.  Disturbance in Allocation Data in Project and Resource Page

    Posted Dec 19, 2017 07:52 AM

    Hi All,

     

    The data value which is showing in the Project>>Team Details page and Resource>>Allocation Details page is different.

     

    Ex: roshan's hard allocation for Dec month in the sample project is 40 in the project team details page but in the resource>>details page for roshan's account for the sample project is 30.

     

    Please do let me know if anyone knows why the issue is causing like this . 

     

    Regards,

    Freddy 



  • 2.  Re: Disturbance in Allocation Data in Project and Resource Page
    Best Answer

    Posted Jan 05, 2018 01:28 PM

    Not certain on this, but are those two different slices?  I know the project team's page utilizes and "instant slice" that is calculated on update, but most other allocation portlets/reports utilize the standard time slices.  

     

    I'd double check that your time slice definitions (specifically the *alloccurve slices) are up to date and the job is running. And, as always, double check your filters. I find that a lot of times I'm bit by the "Booking Status" filter when I see any discrepancies between different views.