  • 1.  CAPPM Advance the Projects

    Posted Jan 12, 2017 12:36 PM

    Good morning, I need information on how to configure the projects in cappm, so that I can see in the portlets the advance actual versus expected progress, both physical and financial.

    Another one question
    Are there any quick configuration reference manual cappm??

    Principio del formulario

     

    Thanks in advance



  • 2.  Re: CAPPM Advance the Projects

    Posted Jan 12, 2017 01:51 PM

    That sounds like baselining. Baseline would be your expected progress and actual situation would be in your current plan.

    First you would need to read through the documentation about baselining and the you would need to set a baseline.