  • 1.  Summary Task Assignments Not Supported

    Posted Aug 26, 2016 06:57 AM

    We get a number of project managers using MSP get the "Summary Task Assignments Not Supported" error when they download their plan and make no changes.

     

    This implies that the resource assignment against the summary task is already in the system.

     

    When investigating we have been unable to either assign a resource to an existing summary task or to change a task with a resource already assigned to a summary task. Which begs the question, how did they make their way in to the system?

     

    Has anyone experienced this? Any ideas on how the original assignments are caused?



  • 2.  Re: Summary Task Assignments Not Supported

    Posted Aug 26, 2016 09:24 AM

    In CA PPM you can only assign resources to Tasks that is the lowest level in WBS. The same goes for OWB.

    That has been adequate.

    Though it is possible to assign resources to summary level items in MS Project, that apparently is not passed to CA PPM.



  • 3.  Re: Summary Task Assignments Not Supported

     
    Posted Aug 30, 2016 07:30 PM

    Hi JonathanDeane76040996 - Did urmas's response help answer your question? If so please mark as Correct Answer. Thanks!