Disable auto ETC based on %allocation

Jump to Best Answer
  • 1.  Disable auto ETC based on %allocation

    Posted 02-09-2017 07:20 AM

    Hello,

    if you add resource to the task for example from gantt to the task his ETC is autopopulated based on his % of allocation for time period of task.

     

    Is there any possibility to disable this auto fill ETC functionality?

     

    Vit



  • 2.  Re: Disable auto ETC based on %allocation
    Best Answer

    Posted 04-19-2017 02:20 PM

    Hi Vit,

     

    If the resource has a planned allocation, ETC value will be given for that resource. If you remove the planned allocation then the ETC will become '0' when assigning that resource to a project. Currently this is by design and unfortunately there is no way to disable this feature. Please let us know if this has answered your question. Thank you!

     

    Kind regards,

     

    Tabish Siddiqui



  • 3.  Re: Disable auto ETC based on %allocation

    Posted 05-03-2017 04:27 AM

    Thank you Tabish,

    I asked just for confirmation if I didn´t miss something.

    Vit