Can we extend the end date for an existing task from XOG or GEL. My attempts to change using XOG aren't working.
Hi,
Have you tried the following:
1. Xog out a project using the prj_projects_read.xml
2. Change the Task Finish Date in the output file
3. Xog in this output file
This changes the project finish date as well, if needed.
Were you able to do the same from Application UI?
Also, do share the input xml, if you can?
Please check project finish date.If project finish date is less then task date xog will not work properly.