  • 1.  prj_blb_slices_m_ETC - table, when dose the value gets stored in the table ?

    Posted Aug 18, 2017 06:52 AM

    Hi All,

     

    I Like to know when dose the value gets stored in the prj_blb_slices_m_ETC table.

     

    i.e : for a project and a resource the start date of the project and start date of the allocation begins on August 2017 month but there is value in the particular table for Jan 2017 month. Any idea why it so happens like this?

     

    Regards,

    Frederic 

     

    SumanPramanik



  • 2.  Re: prj_blb_slices_m_ETC - table, when dose the value gets stored in the table ?

    Posted Aug 18, 2017 07:32 AM

    Check for any task assignments for that period.

     

    Check the below

     

    ETC value of a resource for a project

    https://communities.ca.com/message/241707631

     

     

    NJ 



  • 3.  Re: prj_blb_slices_m_ETC - table, when dose the value gets stored in the table ?

    Broadcom Employee
    Posted Aug 18, 2017 07:36 AM

    Hi Frederic,

     

    The table 'PRJ_BLB_SLICES_M_ETC is the Timeslice for the Monthly ETC slice. More information on timeslice is documented here

     

    https://docops.ca.com/ca-ppm/15-1/en/administration/configure-time-slices 

     

    Regards

    Suman Pramanik



  • 4.  Re: prj_blb_slices_m_ETC - table, when dose the value gets stored in the table ?

    Posted Sep 01, 2017 09:03 AM

    Hi Suman,

     

    In Project >>Team>>Details page , the value of ETC is it fetched from PRJ_BLB_SLICES_M_ETC table?

     

    Regards,

    Frederic