  • 1.  Allocation aggregation issue

    Posted Apr 28, 2017 03:31 PM

    Hi,

     

    One of my PMs just ran into this issue where the allocation value in Team>Detail is not lining up correctly or aggregating correctly. When I export the data, the field is blank.

     

    Example: row two here shows 30 hours of both ETCs and Allocations in April 17. When I look at the aggregation totals in the bottom, the ETCs are correct but the Allocation is off by -30. When I export the data, this resource has 30 hours of ETCs and 0 for Allocations.

     

    Thanks in advance!

     

    allocation aggregation issue



  • 2.  Re: Allocation aggregation issue

    Posted May 02, 2017 12:31 PM

    Are you viewing this data in a pop-up, if so, please try viewing as non pop-up.  I've experienced a similar issue on the task allocations which was resolved by viewing the data in a non pop-up.  My issue has been reported to CA who have recognised as a defect and are working on a solution.



  • 3.  Re: Allocation aggregation issue

    Posted May 11, 2017 09:01 AM

    Hi Roland,

     

    Apologies for my late response. No, I am viewing it within the original browser in Chrome.