I should try to
remove all the time on the effort task with adjustment timesheets
unassign resources from the effort task
delete the effort task, if not possible try to change the ID of the task from ~rmv to something else
remove the global Project management option to create effort task
I do not think you can shorten the effort task from the full project length as that is the functionality