Clarity

 View Only
  • 1.  Task Status on Effort Driven Project

    Posted Jun 29, 2016 07:51 AM

    We have a number of projects that have the % Complete Calculation set to Effort and are in the process of doing a cleanup in the projects.  Some of the tasks that the PMs have created do not have resources assigned to them.  Since the Status and % Complete are not available (greyed out) is there anyway to update these tasks within Clarity or does the project need to be opened in MSP and updated?



  • 2.  Re: Task Status on Effort Driven Project
    Best Answer

    Posted Jun 29, 2016 02:22 PM

    Tried that in v14.4.

    As you say they are not editable while the calculation method is Effort.

    Changed that to Manual which allowed to set the status to Completed and % Complete to 100.

    Changing then back to Effort restored Not Started and 0%.

     

    Appears that is the it is designed and the only way to change them is to have resources assigned with ETC and then to enter actuals.