We are using CA PPM 14.2 and MS Project 2010. We have pending actuals (attribute prpendactsum from the resource object) mapped to MSP resource auxiliary field number2. When a project is opened in MSP the value on all resource records show as 0. My understanding and the way I have seen this in past is if there are no pending actuals there was a value of -1 and if there were pending actuals the amount of the hours would show on the resource. Any suggestions as to why this might not be working?