Hi
Recently we've upgraded clarity from 13.2 to 14.2.
We've custom object as subobject to Project Object. By process, the attributes of Custom object is automatically filled on creation. When I click Save button on the custom object page, the process in project are all initiated.
Initially I thought some of the process in Custom object has some issue. So I put on hold all the processes except the create process in Custom object.
When I click Save, not even editing custom object, initiates all the processes under project. This results in changing lot of attributes in Project object including the status.
All the approved projects are affected.
This seems like a bug. Have anyone faced this issue?
This happenes in Production (Version/Build- 14.2.0.237 ) and also in Dev with Generic Patch 7 (Version/Build- 14.2.0.237 07 16)
Please advise ASAP
Thanks
Sreeram