  • 1.  Date field control?

    Posted Jun 14, 2016 10:08 AM

    Hello, I need to make a date control into project page, i have to force users to put date equal or less than the project finished date.

    This is an example:

    2016-06-14_135203.png

    Do i must create a query to control the date? if yes what paramaters i should used? and if i put a date greater than finished date how i can show an error message?

    I appreciate your help.

    regards



  • 2.  Re: Date field control?
    Best Answer

    Posted Jun 14, 2016 10:58 AM

    A process / trigger (not supported) on enter/update of the date to check against the project's finish date.

     

    NJ



  • 3.  Re: Date field control?

    Posted Jun 14, 2016 12:40 PM

    did i must create a gel script or system action control?



  • 4.  Re: Date field control?

    Posted Jun 15, 2016 01:31 AM

    Gel script, I suppose

     

    NJ



  • 5.  Re: Date field control?

     
    Posted Jun 20, 2016 08:19 PM

    Hi Calemirou   - Did navzjoshi00 's responses help answer your question? If so please mark as Correct Answer. Thanks!



  • 6.  Re: Date field control?

    Posted Jun 21, 2016 10:38 AM

    Trigger may not be supported, but if you are on premise, you can still use it.