Scenario: Add a task in MS Project 2007, Task A 5 day duration ( not effort driven), from start date 2015/07/14 to 2015/07/20, assign a business analyst resource 75% allocation.
Save to CA PPM via CA Clarity PPM Integration.
Result: The loading pattern is "Uniform" when the default was set to "Fixed" and the fix duration is not check marked.
When reopening with MS Project Read-Write, the duration is changed to 1 day and the dates as well.
How can task be created from MS Project Integration, with a fix duration and set allocation, and remain the same when viewing from CA PPM?
Is the loading pattern default to "Fixed" the right setup?