Here i have another odd issue in Version 13.2
Project manager has added few resources in team but not yet assigned any task to them.
Wonder is users are able to add the task by themselves while filling their efforts in the time sheet.
I have checked using user credentials. They have basic team member rights but still they could see all assigned and non assigned tasks when they click on ADD TASK button in their time sheet.
I'm not getting why this is happening. They don't have any special rights.
Please guide me in this regard.