  • 1.  Show financial values in project properties

    Posted Jan 14, 2015 10:24 AM

    Hi Communitie!

     

    We need following information  at project´s propertie page:

     

    Actual Cost.........................................: ok = I have created a calculated attrib Sum(aggr_actual_cost) to show total realized. 

    Cost total............................................: ok = Already exist in Clarity  [Planned Capital Cost] to show total planned cost.

    Actual Cost - Current Year.....................: ? = We need to know how much project spents in current year.

     

    So, how can I put this ACTUAL COST  - CURRENT YEAR in project´s propertie page?

    Looks like a query solution, but in this case I am afraid for database performance issues.

     

    Best regards,

     

    Nei Villas Boas



  • 2.  Re: Show financial values in project properties
    Best Answer

    Posted Jan 14, 2015 10:31 AM


  • 3.  Re: Show financial values in project properties

    Posted Jan 14, 2015 11:09 AM

    Hi Dave,

     

    It will be a challange due my low SQL skill, but maybe this is the only way to do it.

    I am still concerned about performance issue, so I will use a TEST environment.

    Thank you very much for your useful input.

     

    Best regards,

    Nei