  • 1.  Portfolio plan vs Project scenario

    Posted Jul 16, 2014 06:04 AM

    When I need to move project in portfolio because of resource shortage its ok only when I want to move project as is.

    Is there any way to do it on task level? Create scenario with only one task changed start and finish time and the rest tasks will stay as is? But still in regime of What if.

     

     

    Vit



  • 2.  Re: Portfolio plan vs Project scenario

     
    Posted Jul 23, 2014 06:44 PM

    Hi All,

     

    Any ideas here for Vit?

     

    Thanks!

    Chris



  • 3.  Re: Portfolio plan vs Project scenario

    Posted Jul 24, 2014 06:15 AM

    Hi Vit,

    Normally at a portfolio level, the "what if" does not go into such detail.

    You can play with the role demand by clicking on the investment then clicking the role demand tab.

    Then adjust the role demand of the project for that plan.

     

    I'm sure you have picked it up but you can also add in specific roles and have an aggregate of this displayed to highlight the issues.

     

    Hope this helps



  • 4.  Re: Portfolio plan vs Project scenario

    Posted Jul 25, 2014 05:26 AM

    So there is not possibility to choose project scenario in Portfolio plan?